Field erected storage tanks

GRI was contracted by client to engineer, fabricate, and installed 7 new field erected API storage tanks, 2 clarifiers, and 1 shop tank (delivered from our Natchez, MS facility). GRI completed all phases of civil construction as well as all electrical and instrumentation for the project. GRI coated, tested and commissioned the tanks for final approval.


 

34,000 MANHOURS

13 months

$8,346,000

SCOPE OF WORK:

  • Engineering

  • Fabrication

  • All phases of civil construction

  • Underground piping

  • Piping fabrication and install

  • Electrical and instrumentation

  • Coatings

  • Testing

  • Commissioning