train 1 & 2 installation
GRI was contracted to fabricate and install over 14,000 lf of piping. Included in the scope of the contract was civil foundations, setting all process equipment including tanks, vessels, conveyor systems and pumps, grouting and equipment alignment. GRI erected the flare stack, installed process tubing, tested and commissioned the unit.
30,000 MANHOURS
9 months
$2,500,000
SCOPE OF WORK:
Pipe Fabrication
Pipe Installation
Civil Foundations
Tank Setting
Vessel Setting
Installation of Conveyor System
Installation of Pumps
Grouting of Equipment
Equipment Alignment
Flare Stack Erection
Testing
Commissioning